Evaluasi Percepatan Pembangunan Proyek Rusunawa ASN Pemkab Malang Menggunakan Metode Crashing Dengan Sistem Sihft Kerja

GUNASTI, AMRI (2019) Evaluasi Percepatan Pembangunan Proyek Rusunawa ASN Pemkab Malang Menggunakan Metode Crashing Dengan Sistem Sihft Kerja. Teknik Sipil, Fakultas Teknik, Universitas Muhammadiyah Jember.

[img] Text
PeerReview10.pdf

Download (519kB)
[img] Text
10. Turnitin.pdf

Download (2MB)
[img] Text
10. Dokumen Lengkap.pdf

Download (1MB)

Abstract

In construction projects there are three things that must be considered, namely time, cost and quality. However, reality shows that there is still often a delay time of implementation. One way to overcome delay in construction projects is to do with the crashing. This research was conducted on the project of the construction of the building Rusunawa ASN Malang Regency. The method of crashing used by way of a work shift. The calculation of the needs of the work shift using the guidelines for the calculation of Unit Price Analysis of Workers (AHSP) in 2018. The results showed that the project can be accelerated for 24 working days, so the duration of the project which was originally 197 working days to 173 days of work. Direct costs the project has increased from Rp.12.763.192.497.58 in 197 days to Rp. 12.937.000.000.00 in 173 days (up 1,3554%).

Item Type: Peer Review
Uncontrolled Keywords: Crashing, Unit Price Analysis of Workers 2018, shift work, and Rusunawa
Subjects: 600 Technology and Applied Science > 620 Engineering > 624 Civil Engineering
Divisions: Faculty of Engineering > Department of Civil Engineering (S1)
Depositing User: Amri Gunasti
Contact Email Address: amrigunasti@unmuhjember.ac.id
Date Deposited: 01 Aug 2022 02:48
Last Modified: 01 Aug 2022 02:48
URI: http://repository.unmuhjember.ac.id/id/eprint/14652

Actions (login required)

View Item View Item