Detail Tugas Akhir

(PEER REVIEW + SIMILARITY + DOCUMENT) EVALUASI PERCEPATAN PEMBANGUNAN PROYEK RUSUNAWA ASN PEMKAB MALANG MENGGUNAKAN METODE CRASHING DENGAN SISTEM SIHFT KERJA

GUNASTI, AMRI (2020) (PEER REVIEW + SIMILARITY + DOCUMENT) EVALUASI PERCEPATAN PEMBANGUNAN PROYEK RUSUNAWA ASN PEMKAB MALANG MENGGUNAKAN METODE CRASHING DENGAN SISTEM SIHFT KERJA. Teknik Sipil, Fakultas Teknik, Universitas Muhammadiyah Jember.

Berkas Tugas Akhir

PDF
Text
PeerReview10.pdf
PDF
Text
10. Turnitin.pdf
PDF
Text
10. Dokumen Lengkap.pdf

Abstract

In construction projects there are three things that must be considered, namely time, cost and quality. However, reality shows that there is still often a delay time of implementation. One way to overcome delay in construction projects is to do with the crashing. This research was conducted on the project of the construction of the building Rusunawa ASN Malang Regency. The method of crashing used by way of a work shift. The calculation of the needs of the work shift using the guidelines for the calculation of Unit Price Analysis of Workers (AHSP) in 2018. The results showed that the project can be accelerated for 24 working days, so the duration of the project which was originally 197 working days to 173 days of work. Direct costs the project has increased from Rp.12.763.192.497.58 in 197 days to Rp. 12.937.000.000.00 in 173 days (up 1,3554%).

Informasi Item

Item Type Peer Review
Keywords/Kata Kunci Crashing, Unit Price Analysis of Workers 2018, shift work, and Rusunawa
Subjects 600 Technology and Applied Science > 620 Engineering > 624 Civil Engineering
Divisions Faculty of Engineering > Department of Civil Engineering (S1)
Date Deposited 18 Aug 2022 01:48
Last Modified 18 Aug 2022 01:48
URI https://repository.unmuhjember.ac.id/id/eprint/15153

Actions (login required)

View Item
View Item
Ada yang bisa kami bantu?